A vacuum disc filter site performance test should verify agreed production, cake moisture, and other specified results under defined feed and utility conditions. The results must come from the same qualifying operating periods. Maximum throughput from one run and minimum moisture from another do not demonstrate that the filter meets both requirements together.
The checklist below is a planning framework for owners, suppliers, and commissioning teams. The project's agreed test procedure determines the actual limits, methods, duration, and acceptance decision.
A factory inspection, a site installation check, and a slurry performance run answer different questions. Equipment can be assembled correctly and operate mechanically without yet having demonstrated the required process duty.
Define which checks belong to the site's acceptance scope. Confirm that commissioning prerequisites are complete before starting a performance run, using the project's approved procedures. The vacuum disc filter commissioning checklist provides related preparation questions.
Keep unresolved installation or control findings visible. Starting a production trial should not cause open findings to disappear from the project record.
Write down where the evaluated system begins and ends. Is the commitment for the filter alone, or for a station including feed delivery, vacuum equipment, filtrate handling, and cake conveying?
Specify the feed conditions under which the result is to be demonstrated. Include the relevant solids concentration, particle-size distribution, ore blend, temperature, and chemistry information. Define the utility conditions and the permitted operating settings as well.
Agree in advance how out-of-range conditions will be handled. An interruption caused by a shared conveyor may affect station production even if the filter operates correctly. Recording it separately allows the parties to interpret both equipment and station performance without losing the event.
The acceptance sheet should identify each metric, its boundary, its method, and its decision rule.
| Item | Definition to agree before testing |
|---|---|
| Production | Dry-solids mass per unit time, measurement point, and time denominator |
| Cake moisture | Wet or dry basis, sampling location, laboratory method, and applicable limit |
| Filtrate quality | Relevant solids measurement, sampling point, and requirement |
| Utilities, if included | Equipment boundary, meter, units, and qualifying operating period |
| Run continuity | Required duration and treatment of trips, pauses, or interrupted feed |
| Acceptance decision | Whether a limit applies to each result, an average, or another specified statistic |
These are proposed fields for a project plan, not universal acceptance thresholds. Metso's filtration test-work description similarly lists capacity, moisture, filtrate quality, and media among test-report outputs. It does not prescribe the contractual site procedure for another supplier's equipment.
If production is measured as wet cake mass, the corresponding moisture must represent that same material and interval. Account for travel time between the filter discharge and the measurement or sampling point where relevant.
For moisture expressed on a wet basis:
Dry-solids mass = wet cake mass × (1 − wet-basis moisture fraction)
As an illustrative calculation, 100 tonnes of wet cake at 12% wet-basis moisture contains 88 tonnes of dry solids. If that material was collected over four hours, the average dry-solids rate for that period is 22 tonnes per hour. These invented numbers explain the calculation; they are not a Tongzhiren performance claim or a recommended acceptance limit.
The cake moisture basis guide explains why a moisture percentage must retain its reporting basis.
Agree where samples will be collected, the collection frequency, sample handling, identification, and analysis method. Define how individual increments will represent the discharge stream and how any composite will be prepared.
Do not select only cake that looks dry or is easiest to reach. Use approved sampling points and procedures that keep personnel clear of moving machinery.
Connect every sample to timestamps and operating records. If duplicate samples or retained samples will be used to investigate disagreements, agree those arrangements before testing. Where a moisture method can remove substances other than water, have the laboratory establish how the result should be interpreted.
Maintain an event log alongside the measurements. Record feed disturbances, filter trips, cloth changes, utility changes, and adjustments made during the run.
State whether reported production uses total elapsed time or qualifying operating time. Both can be informative, but they answer different questions. If a period is excluded under the agreed procedure, retain its timestamps and the reason for exclusion in the report.
Define stabilization and restart rules beforehand. A run assembled afterward from favorable fragments is difficult to assess unless that treatment was explicitly part of the agreed method.
Check the calibration status and suitable range of the instruments used. Record known limitations in mass measurement, sampling, moisture analysis, and time alignment.
If a result sits close to an acceptance limit, apply the previously agreed decision rule. Do not add an arbitrary tolerance or change the averaging method after seeing the result. A repeat test or improved measurement may be needed where the available evidence cannot support a clear conclusion.
Preserve raw observations and calculations so another reviewer can reproduce the reported result.
The final record should identify the equipment, procedure revision, feed conditions, settings, measurement methods, raw data, calculations, excluded periods, and conclusions. Separate demonstrated results from requirements that remain untested.
Where a requirement is not met, document the observation and the agreed next action. Distinguish a measured shortfall from a proposed explanation of its cause.
For a new project, use the quotation scope checklist to place responsibilities and performance boundaries in the supplier discussion early. Contact Tongzhiren Filtration with the intended duty and acceptance requirements to discuss the test scope.
Only if the relevant process duty was actually demonstrated under applicable agreed conditions. Mechanical operation alone does not establish slurry performance.
They can be shown as separate observations, but they do not establish simultaneous compliance unless both were achieved during the same qualifying conditions.
Use a duration agreed for the project that supports the intended operating claim. There is no single duration appropriate for every feed and acceptance scope.
Record the change and apply the agreed feed-envelope and restart rules. Keep affected data traceable even if it is excluded from the acceptance calculation.